All calculators / Subpanel and service wire calculator
What size wire for a 200 amp service?
4/0 AWG aluminum for a 200 A service
A 200 A main service to a house needs at least 4/0 AWG aluminum service-entrance conductors (NEC 310.12 sizes them at 83% of the rating), with a 4 AWG copper grounding electrode conductor.
Assumes a 200 A main service to a single-family house, aluminum service-entrance cable, a 50 ft run from meter to panel. Change the inputs.
200 amp service wire
| Conductor and run | Answer |
|---|---|
| Aluminum, 25 ft | 4/0 AWG aluminum for a 200 A service |
| Aluminum, 100 ft | 4/0 AWG aluminum for a 200 A service |
| Aluminum, 200 ft | 4/0 AWG aluminum for a 200 A service |
| Copper, 25 ft | 2/0 AWG copper for a 200 A service |
| Copper, 100 ft | 2/0 AWG copper for a 200 A service |
| For comparison: 200 A subpanel feeder, aluminum | 250 kcmil aluminum feeder, 200 A breaker |
Service conductors only. A subpanel fed at the same rating needs the full ampacity: see the subpanel pages.
The 83% rule
A house never draws its whole service rating for long, so NEC 310.12 lets the conductors of a single-family dwelling's main service be sized at 83% of the rating. For 200 A that means conductors rated at least 166 A: 2/0 copper or 4/0 aluminum in the 75°C column. That is where the familiar "4/0 aluminum for 200 amps" comes from.
It applies only to the service or main feeder carrying the whole dwelling. A 200 A subpanel feeder needs conductors rated the full 200 A, which is one or two sizes larger; the last row of the table shows it.
Before anyone touches it
Service-entrance conductors run from the meter to the main panel with no breaker ahead of them. Replacing or upsizing them needs a permit, a licensed electrician, and usually the utility to pull the meter or disconnect the drop. The utility also sets the rules for its side of the meter. Treat this page as a way to check a quote, not as instructions.
Run it for your house
The calculator below starts from the assumptions above. Change any input and the answer updates.
4/0 AWG aluminum for a 200 A service
A 200 A main service to a house needs at least 4/0 AWG aluminum service-entrance conductors (NEC 310.12 sizes them at 83% of the rating), with a 4 AWG copper grounding electrode conductor.
- The 83% allowance is only for the service or main feeder that carries an entire single-family dwelling's load. A subpanel feeder needs the full rating.
- The service drop or underground lateral up to the meter usually belongs to the utility and follows its rules. This size is for the service-entrance conductors from the meter to the main panel.
- Service work needs a permit, a licensed electrician, and usually the utility to cut power. Service conductors have no breaker upstream: never work on them yourself.
How we got there
| Feeds | The main service of a single-family home | NEC 310.12: conductors rated at least 83% of 200 A = 166 A |
|---|---|---|
| Circuit | 200 A circuit | 240 V |
| Load | 166.0 A | |
| Breaker | 200 A double-pole | next standard size up |
| Wire type | SER / feeder cable, 75°C terminals | 75°C ampacity column |
| Smallest wire for the breaker | 4/0 AWG aluminum | 180 A (NEC 310.16) |
| Voltage drop over 50 ft | 0.7% | 1.7 V at 166.0 A |
| Grounding electrode conductor | 4 AWG copper | NEC Table 250.66, to the ground rods / water pipe |
What to look for
Examples only, not endorsements: model names checked 2026-11-26. Confirm the exact capacity on the spec sheet before you buy. We earn nothing from these.
Questions
Can I use 4/0 aluminum for a 200 amp service?
Yes, 4/0 aluminum is the NEC 310.12 size for a 200 A single-family service in the 75°C column, if the meter base and main lugs are rated for aluminum. Long runs may need a size up for voltage drop.
What size ground rod wire?
The grounding electrode conductor to the ground rods follows NEC Table 250.66: 8 AWG copper for services up to 2 AWG copper or 1/0 aluminum, 4 AWG copper for 2/0 copper or 4/0 aluminum. Many inspectors accept 6 AWG copper to rods regardless.
Sources
Checked 2026-11-26. Full method on the methodology page.